Tamleek Al Nahdi Wahat Al Rehab Project
16 Feb 2026

Al Rehab Oasis Project

90%Overall▲ +14% · vs previous visit

Main video

Engineering Report

The Oasis Al-Rehab project was visited on 2026-02-16, with the overall completion rate reaching 90%. Significant progress is evident in both exterior and interior finishing works, with the concrete structure and foundations 100% complete. The project is in the advanced stages of facade installation and interior painting.
Detected changes
Exterior Facades100%

Installation of wood-texture and gray cladding panels is largely complete, with scaffolding removed from most building facades.

Interior Finishing Works95%

Execution of plastering and primary painting (primer) for walls and ceilings, along with the preparation of concealed air conditioning ducts.

General Site and Roof90%

Commencement of insulation and tiling works on the roof, with construction materials and supplies staged in the ground setback area.

Mechanical and Electrical Works85%

Installation of electrical switch boxes and wiring, in addition to the installation of sewage systems and bathroom fixtures.

Progress reading

The visual appearance is consistent with the surge in finishing completion from 40% to 80%, as work has transitioned from the structural and masonry stages seen in previous photos to the exterior cladding and interior painting phases. The progress of mechanical works to 90% is reflected in the completion of drainage and HVAC installations.

vs previous visit

Compared to the photos from the previous visit (21-26), a radical transformation is evident; while the facades were previously red brick and cement under scaffolding, they now feature their final modern design. Additionally, interior works have progressed from the structural foundation stage to the plastering and painting phase.

Expected next milestones

Installation of aluminum doors and windows, completion of lighting and final switches, interior floor tiling, and general site cleaning.

Progress

0%OverallAverage item progress
2/5 completeavg ▲ +14%
Finishing▲ +40%
0%
Concrete Works
0%
Electrical▲ +20%
0%
Mechanical▲ +10%
0%
Foundations
0%

Drone Shots

Site Photos

360 Tours

3D Model