Al Rehab Oasis Project
Main video
Engineering Report
Detected changes
Completion of the entire structural frame of the building, with the external and internal wall masonry finished using cement and red blocks, and the architectural openings for windows and doors clearly visible.
Installation of green and black PVC piping for plumbing and electrical works within the walls and ceilings, along with the fitting of electrical distribution boxes.
Commencement of plastering works in some internal rooms, while preparation continues for the remaining spaces to receive finishing layers.
The building is in the advanced structural shell stage, where the external facades appear fully built without the start of external plastering or final painting works.
Progress reading
Visual observations align with the reported completion rates; the 100% completion of the concrete structure reflects the building's visible status. Mechanical works (80%) and electrical works (60%) are evident through the density of internal installations, while finishing works are in their initial stages (40%), currently focused on plastering.
vs previous visit
There is no previous visit for comparison
Expected next milestones
Completion of internal and external plastering works, commencement of door and window frame installation, and ongoing electrical wiring pull-through.