Tamleek Al Nahdi Downtown Project
10 Nov 2025

Downtown Project

69%OverallFirst visit — no previous comparison.

Main video

Engineering Report

Significant progress has been observed in the exterior finishing and facade works of the Nahdi Downtown project. The buildings are in advanced stages of external plastering and the installation of windows and aluminum, while construction work continues on the adjacent building.
Detected changes
External Facades95%

Completion of plastering (rendering) and primary base coats for the majority of external surfaces.

Windows and Openings90%

Installation of aluminum frames and glazing for the main and side facades.

Roof85%

Installation of rooftop water tanks and preparation of waterproofing and thermal insulation for the roofs.

Adjacent Building (Left Side)95%

Continuation of carpentry and reinforced steel works for the ceiling of one of the typical floors.

Progress reading

The images show that the project has fully surpassed the concrete structure phase for the main building and is currently in the final facade finishing stage. Meanwhile, the adjacent building remains at the structural frame stage, indicating a discrepancy in the execution timelines between the project's blocks.

vs previous visit

No previous visit available for comparison

Expected next milestones

Completion of final facade painting, removal of remaining scaffolding, and commencement of paving and general site landscaping works.

Progress

0%OverallAverage item progress
2/5 complete
Finishingnew
0%
Concrete Worksnew
0%
Electricalnew
0%
Mechanicalnew
0%
Foundationsnew
0%