Aali Al Rehab Project
Main video
Engineering Report
Detected changes
Installation of grey panels and wood-plastic composite (WPC) cladding is largely complete, with only minor sections remaining on the upper floors.
Construction and finishing works for the roof rooms are ongoing, with wooden scaffolding still in place.
Window openings are being prepared for final installation, with some frames already visible.
The site is being cleared of major construction debris, and preparations for the sidewalks have commenced.
Progress reading
The images align with the declared completion rates; the finished concrete structure reflects 100% completion, while the facades and exterior finishes show tangible progress consistent with the 95% mark. Electromechanical works are not clearly visible, but the absence of external conduits suggests internal progress.
vs previous visit
There is no previous visit for comparison
Expected next milestones
Installation of window glazing, completion of the roof annex works, and commencement of final asphalt paving and external perimeter lighting.