Masa Al-Fayhaa Project
Main video
Engineering Report
Detected changes
Completion of concrete pouring for all typical floors up to the roof and upper penthouse.
Commencement of exterior and interior masonry work using cement blocks on the lower and middle floors.
Removal of formwork and scaffolding from the floors where concrete pouring has been completed.
المبنى مغطى بالكامل بالبلوك الأسمنت، ولم تبدأ أعمال اللياسة الخارجية أو تركيب الواجهات بعد.
Progress reading
Although the report indicates a 0% completion rate, visual evidence confirms that the structural phase has been significantly surpassed (estimated at over 80% of the concrete skeleton). The building now appears at its full height, a major advancement compared to previous photos which showed only the initial stages of the structure.
vs previous visit
The difference is substantial; during the previous visit (January 2026), the building was in the early structural stages (reinforcement and pouring of lower floors), whereas in the current visit (May 2026), the concrete skeleton is fully completed, with the typical floors and the roof annex clearly finalized.
Expected next milestones
Completion of blockwork, commencement of initial electrical and plumbing installations, and the start of plastering or exterior facade works.