Tamleek Al Nahdi Safwat Al Salamah Project
15 Feb 2026

Safwa Al-Salama Project

78%Overall▲ +18% · vs previous visit

Main video

Engineering Report

Aerial and perspective imagery shows significant progress in the building's exterior and final finishing works. Exterior plastering and the installation of modern facades (cladding or final paint) are largely complete. Additionally, roof tiling and parapet installation have been finished, indicating the project's transition from the structural phase to advanced finishing stages.
Detected changes
Exterior Facades100%

Completion of painting and final facade finishes, and dismantling of scaffolding

Rooftop95%

Completion of insulation, tiling, and installation of water tanks

External Perimeter90%

Site cleaning and removal of major construction debris previously present

Progress reading

Although the textual data indicates 0%, the images visually confirm that the project is in the final finishing stages. The transition from the red brick visible in the previous visit to the currently completed facades reflects a significant leap in actual progress.

vs previous visit

During the previous visit (2025-11-06), the building was a concrete shell with incomplete red brickwork and plastering. In the current visit, the building's facades are fully completed in white and gray, featuring rooftop seating areas and artificial landscaping on the balconies.

Expected next milestones

Completion of interior finishing, installation of elevators, connection of final utilities (electricity and water), and unit handover.

Progress

0%OverallAverage item progress
2/5 completeavg ▲ +18%
Finishing▲ +39%
0%
Concrete Works
0%
Electrical▲ +30%
0%
Mechanical▲ +20%
0%
Foundations
0%