Tamleek Al Nahdi Taj Al Rawdah Project
6 Nov 2025

Taj Al-Rawda Project

42%OverallFirst visit — no previous comparison.

Main video

Engineering Report

A field visit to the Taj Al-Rawda project site was conducted on November 6, 2025. Aerial imagery reveals significant progress in the concrete structure's construction. The building is currently in an advanced stage of formwork and reinforcement for the roof of the final floor (annex), following the completion of column and slab casting for the typical lower floors.
Detected changes
Structural Frame - Final Floor Roof95%

Completion of formwork and reinforcement steel distribution for the entire upper roof slab, with labor present on-site.

Typical Floors90%

Completion of concrete pouring for columns and slabs across three typical floors below the current working level.

Site Perimeter85%

Organization of the work area and presence of protective barriers around the project, with ongoing external wooden shoring works.

Progress reading

Although the completion rate recorded in the system is 0%, visual evidence confirms that the structural phase has been significantly surpassed, with work reaching the roof of the upper annex. This indicates a discrepancy between the administrative updates and the actual field progress, which shows advanced stages in the concrete skeleton.

vs previous visit

No previous visit available for comparison

Expected next milestones

Casting the roof slab of the final floor, commencement of masonry work (blockwork), and the start of initial electrical and plumbing installations.

Progress

0%OverallAverage item progress
1/5 complete
Finishingnew
0%
Concrete Worksnew
0%
Electricalnew
0%
Mechanicalnew
0%
Foundationsnew
0%