Taj Al-Rawda Project
Main video
Engineering Report
Detected changes
Completion of formwork and reinforcement steel distribution for the entire upper roof slab, with labor present on-site.
Completion of concrete pouring for columns and slabs across three typical floors below the current working level.
Organization of the work area and presence of protective barriers around the project, with ongoing external wooden shoring works.
Progress reading
Although the completion rate recorded in the system is 0%, visual evidence confirms that the structural phase has been significantly surpassed, with work reaching the roof of the upper annex. This indicates a discrepancy between the administrative updates and the actual field progress, which shows advanced stages in the concrete skeleton.
vs previous visit
No previous visit available for comparison
Expected next milestones
Casting the roof slab of the final floor, commencement of masonry work (blockwork), and the start of initial electrical and plumbing installations.