Masa Al-Fayhaa Project
Main video
Engineering Report
Detected changes
Completion of the ground floor columns and slab casting, with carpentry and steelwork underway for the typical floors (two floors above ground level are currently visible).
The previous excavation area has been fully backfilled, and the structural framework has been constructed above it.
The staging area has been organized, and a tower crane is now operational on-site.
Progress reading
Although the data records a 0% completion rate, visual evidence confirms that the foundation stage has been surpassed and structural concrete work for the upper floors has commenced. This suggests an upcoming update to the official progress percentages to align with the actual site reality.
vs previous visit
There is a significant difference between the two visits; previous images showed the site in the initial excavation phase with a single excavator present, whereas current images show a standing structure with several floors and the completion of the foundations and ground floor columns.
Expected next milestones
Completion of concrete pouring for typical floor slabs, commencement of masonry (blockwork), and the start of initial electrical and plumbing installations.