Safwat Al-Salama Project
Main video
Engineering Report
Detected changes
Completion of casting the columns and roof for the final floor and the upper annex
Execution of red brick masonry for the front and side facades of the typical floors
Construction of the roof parapet and annex rooms using black cement blocks
Presence of excavation equipment (excavator) on the adjacent land and preparation of the site's perimeter fence
Progress reading
The images show that the project has significantly progressed beyond the core structural phase, with work currently focused on closing the exterior walls. The use of red clay bricks for the residential floors and cement blocks for the annex indicates adherence to the approved technical plans.
vs previous visit
No previous visit available for comparison
Expected next milestones
Commencement of external plastering works, initial electrical and plumbing installations, and the installation of metal window frames.