Tamleek Al Nahdi Taj Al Rawdah Project

Overview

Completion details

0%Overall completionAverage item progress
2/5 completeavg ▲ +27%
Finishing▲ +20%
0%
Concrete Works▲ +40%
0%
Electrical▲ +30%
0%
Mechanical▲ +44%
0%
Foundations
0%
Overview

Progress timeline

How completion evolved across field visits — newest first.

  1. Latest visit11 Mar 2026Taj Al-Rawda ProjectView visit
    69%▲ +27%
    Overall · 11 Mar 2026
    Finishing50%Concrete Works100%Electrical40%Mechanical54%Foundations100%
  2. 6 Nov 2025Taj Al-Rawda ProjectView visit
    42%
    Overall · 6 Nov 2025
    Finishing30%Concrete Works60%Electrical10%Mechanical10%Foundations100%

A project that allows for weekly progress tracking supported by photos and field reports via an interactive calendar documenting the implementation stages.

Features

Surveillance cameras
Two elevators
Independent external water tanks
Dedicated parking

Location

Register interest

Register your interest

Leave your details and our sales team will reach out.

+966
Project alertsShareChat on WhatsApp